Army delays detonating "catastrophically hazardous" lead azide amid fear, anger
November 21, 2026 Development Source: Ars Technica
Share this article
In an environmental assessment released Wednesday, the Army said that trying to move the lead azide from its current position for any reason was ruled out. Any sloshing or physical shock from loading, transporting, or burying the barrels for safer detonation would create “an unacceptable safety risk and a high probability of accidental, uncontrolled detonation.”
The military considered neutralizing the lead azide using a chemical reagent, but again ruled it out because it said the process would require handling the lead azide over an extended period, with barrels neutralized at a rate of 3 to 10 per day. “The chemical neutralization process requires significantly more ‘hands-on’ time and physical manipulation of the drums by personnel over a prolonged 7- to 22-day period, drastically increasing the probability of accidental, fatal detonation during handling,” the Army wrote in its assessment.
In all, the Army considered a controlled, mitigated “Blow-in-Place” plan the best option, and it specifically planned for a fall detonation. The Army said the fall weather would “take advantage of periods of reduced thermal cycling and to ensure the lowest impact to facility operations and local agriculture (harvesting).”
According to an emergency permit for the detonation from the Environmental Protection Agency, the plan is to place explosive charges and an accelerant on or near each of the ECMs.
The Army intends to try to mitigate the detonation’s impact with a few simple methods. Those include lime-fill and sand-fill barriers around the ECMs, water cannons and misters to control lead dust in the wake of the explosion, and timing the detonation with ideal weather conditions—avoiding high winds that could increase the area exposed to the plume or, conversely, a thermal inversion that could trap the plume in one place.
Iowa’s governor-elect, Rob Sand, wrote on social media that an “unacceptable lack of communication and clarity has made Iowans understandably concerned and angry about this situation.”
Political leaders in nearby Illinois also chimed in, sending a letter to Telle and EPA Administrator Lee Zeldin, expressing “grave concerns” over the plan.
“Alongside our neighbors in Iowa, we are also demanding answers about how this could affect our people’s health and safety,” Illinois Governor JB Pritzker wrote on social media.
On Thursday, prior to the announcement of a delay, environmental groups filed a lawsuit seeking a court-ordered pause of the detonation. The groups alleged, in part, that the EPA approved the plan “without full consideration of less dangerous alternatives that would avoid widespread dispersal and deposition of toxic lead; and inadequate public notice of the plan to open-detonate hazardous waste due to the extraordinarily rushed timeline set by the Army.”
Friday morning, the Army, Department of Health and Human Services, and EPA released a joint statement saying:
The entire interagency is working together to ensure that the controlled detonation in Middletown, Iowa is conducted in the safest fashion possible. Officials have been meticulously planning for this event since March, and all agencies involved are prepared to take the most extreme mitigation measures available to ensure there is no risk to the public and any disruptions are minimized. The entire Trump administration will continue to engage with state and local officials, as well as the broader community, to keep all apprised of updates as they arise.
Notably, in June, Zeldin listed the EPA’s work with Iowa’s lead azide as one of the top “100 environmental victories that showcase EPA’s unwavering dedication to protecting American families.” The work was number 60 on the list, described as providing “critical emergency support to Iowa Army Ammunition Plant, deploying technical experts for 68 deteriorating drums of explosive lead azide.”